Gantt: Add time-based weighting into percent complete calcs

Currently % complete calcs for summary tasks are based solely on the sum of % complete per child task / number of child tasks (x%+y%+z%)/3. In this way, a small scale task of 1 or 2 days has a large impact on summary % complete whereas a large task of 60 days has a small impact. Request is to add in weighting based on duration (end date - start date).